The South Sumatra Light Rapid Transit (, lit. "South Sumatra Integrated Rail Line", shortened to LRT Sumatera Selatan or LRT Sumsel), colloquially known as LRT Palembang or Palembang LRT, is an operational light rapid transit system in Palembang, South Sumatra, Indonesia which connects Sultan Mahmud Badaruddin II International Airport and Jakabaring Sport City. It is the first practical modern light rapid system to operate in Indonesia. It was also the first rail line as a rapid transit system in the country.
The system is owned by Directorate General of Railways, Ministry of Transportation of the Republic of Indonesia, Government of South Sumatra, and Government of Palembang; PT Kereta Api Indonesia was appointed to operate the system.
Starting construction in 2015, the project was built to facilitate the 2018 Asian Games and was completed in mid-2018, just a few months before the event. Costing Rp 10.9 trillion for construction, the system utilizes trains made by local manufacturer PT INKA. The system's only line has a total of 13 stations, fully grade-separated by viaduct.
Because Palembang was chosen to host the 2018 Asian Games, the project was pushed to be completed before the event was scheduled to begin. Groundbreaking for the project occurred in November 2015, with state-owned company Waskita Karya being appointed as the primary contractor following the issuance of Presidential Regulation 116 of 2015 on Acceleration of Railway Train Operation in South Sumatera Province. The contract, which was signed in February 2017, was initially valued at Rp 12.5 trillion. Construction was scheduled for completion in February 2018, with commercial service beginning in May 2018. However, the completion date was moved to June 2018 with operations beginning in July, only one month before the Asian Games.
A test run was done on 22 May 2018. It was later inaugurated by President Joko Widodo on 15 July 2018. Operations for the LRT started on 1 August, several days before the Jakarta LRT began running, making it the first operational LRT system in the country. The final value of the contract was Rp 10.9 trillion (US$755 million). The reduction in cost was due to a review by supervising consultants from SMEC Holdings. Close to the start of the event, the trains often encountered operational issues. Waskita initially paid for the construction, with the government reimbursing the fees over a four-year period.
Prominent opposition figure and Gerindra leader Prabowo Subianto criticized the cost of construction, claiming that typical LRT lines worldwide cost US$8 million/km to construct while the Palembang LRT cost US$24 million/km. As a comparison, the cancelled Sheppard East LRT in Toronto would have cost US$56.7 million/km. The Palembang LRT project leader compared the higher cost to those of other projects in neighboring countries: the Kelana Jaya line (US$65.52 million/km) and the Manila Light Rail Transit Line 1 extension (US$74.6 million/km).
The electrical trains operate on 750 V DC voltage. Individual carriages, made from stainless steel, have a roof height of and a floor height of . The gap between is , with the total length of the current trains (3 carriages) at . The trains are assembled by PT INKA, with around half of the components manufactured locally.
Throughout the first half of 2025, the service had 2.2 million passengers.
|
|